Version 50 (modified by pmccormack, 3 years ago)

--

Team Name: Econopia

Educational Objective:

MI-E2: Describe the impact of governmental policy (sanctions, tariffs, treaties) on that country and on other countries that use its resources.

Management Plan

Team Members

NAME PHONE EMAIL Work Log POSITION
Paul McCormack (303) 847-5365 <pjm32008@mymail.pomona.edu> WorkLogPaul random person
Colin Bundschu (909) 480-5141 <cbundschu@hmc.edu> WorkLogColin random person
Helen Wu (415) 518-1076 <xiaoyingw12@gmail.com> WorkLogHelen random person
Stephen Levine (214) 801-4926 <slevine@hmc.edu> WorkLogStephen random person

Scheduled Meetings

Day of Week Date Time Location Notes link
Friday (1st week) 9/2/11 3:00pm LSC Meeting_1_Notes
Monday (1st week) 9/5/11 4:15pm LSC Meeting_2_Notes
Tuesday (2nd week) 9/6/11 11:00am LSC Meeting_3_Notes
Friday (2nd week) 9/8/11 3:00pm LSC Meeting_4_Notes
Monday (2nd week) 9/12/11 4:00pm LSC Meeting_5_Notes
Tuesday (3rd week) 9/12/11 11:00am LSC Meeting_6_Notes

Phase 1

Deliverable Due Date Point value Grade Distribution
ManagementPlanDoc 9/1,9/6,9/13,9/20 80 PM(25%) CB(25%) HW(25%) SL(25%)
CompetitiveAnalysis 9/6 50 PM(25%) CB(25%) HW(25%) SL(25%)
HighConcept 9/6 50 PM(25%) CB(25%) HW(25%) SL(25%)
CustomerElicitation 9/6,9/13 50 PM(25%) CB(25%) HW(25%) SL(25%)
TechnologyAssessment 9/13 50 PM(25%) CB(25%) HW(25%) SL(25%)
UseCases 9/13 50 PM(25%) CB(25%) HW(25%) SL(25%)
Prototype 9/20 75 PM() CB() HW() SL()
Proposal 9/20 75 PM() CB() HW() SL()
GameTreatment 9/20 5 PM() CB() HW() SL()

Goals

Status: new (11 matches)

Ticket Summary Owner Type Priority Milestone Component
#94 V1 Release: Create installer or single executable due 12-9 [2 hr] somebody task critical milestone4 component1
#185 V1: Final Report - Background [.5 hr] hwu task major milestone4 component1
#186 V1: Final Report - Requirements [1 hr] cbundschu task major milestone4 component1
#187 V1: Final Report - Design [.5 hr] pmccormack task major milestone4 component1
#188 V1: Final Report - Testing [.5 hr] slevine task major milestone4 component1
#189 V1: Final Report - Results[2 hr] hwu task major milestone4 component1
#191 Management Plan 12-6 [1 hr] hwu task major milestone4 component1
#192 Code Prototype Update 12-6 [.7 hr] cbundschu task major milestone4 component1
#183 game sometimes crashes when hidden with "Visual C++ Runtime 9.0" error in exe mode somebody defect minor milestone4 component1
#190 V1: Final Presentation [1 hr] everyone task minor milestone4 component1
#193 game icon doesn't appear on Windows 7 slevine defect minor milestone4 component1

Status: closed (181 matches)

Ticket Summary Owner Type Priority Milestone Component
#15 Management Update 9/13 Helen, Paul task critical milestone1 component1
#22 Postmortem Phase 1 hwu task critical milestone2 component1
#23 1st Architectural Design Draft: Use cases - Due 9/27 [30 min] hwu task critical milestone2 component1
#24 Management Plan 9/22 Alpha Use Cases Rationale pmccormack task critical milestone2 component1
#25 Management Plan 9/22 Phase 2 Goal Stack somebody task critical milestone2 component1
#27 Management Plan 9/22 Goal Plan slevine task critical milestone2 component1
#37 1st Architectural Design Draft: Domain Diagram Due 9-27 [30 min] hwu task critical milestone2 component1
#38 1st Architectural Design Draft: Initial Class Diagram Due 9-27 [1-2hr] Stephen task critical milestone2 component1
#39 1st Architectural Design Draft: Sequence Diagrams due 9-27 [1hr] Paul task critical milestone2 component1
#43 Prototype. UC Make Policy: incorporate resource clicking into popups [ goal = 10-11, t = 1hr] Stephen task critical milestone2 component1
#47 Management plan update 9/27 hwu task critical milestone2 component1
#48 Second Architectural Design Draft: Important components of class interface - Due 10-4 [1 hour] Colin task critical milestone2 component1
#49 Second Architectural Design Draft: I/O specifications - Due 10-4 [1 hr] Stephen task critical milestone2 component1
#50 Second Architectural Design Draft: Underlying models and algorithms - Due 10-4 [1 hr] pmccormack enhancement critical milestone2 component1
#53 Initial UI Design - Due 10-4 [2hrs] Helen task critical milestone2 component1
#62 Management plan update 10/4 Due 10-4 [2hr] hwu task critical milestone2 component1
#63 Architectural Design Review Package Due 10-6 [1hr] hwu task critical milestone2 component1
#64 Design Review Use Cases Due 10-11 [1hr] hwu task critical milestone2 component1
#65 Design Review Other Models Due 10-11 [1.5hr] Colin task critical milestone2 component1
#66 Design Review Class Diagram Due 10-11 [2hr] Stephen task critical milestone2 component1
#67 Design Review Sequence Diagrams+Buildability+Extensibility Due 10-11 [1.5hr] pmccormack task critical milestone2 component1
#69 Test Plan: Main Due 10-11 [1hr] Stephen task critical milestone2 component1
#77 Management Plan Update Due 10-11 [t = 2hr] hwu defect critical milestone2 component1
#78 Final Architecture Due 10-20 [3 hr] Everyone task critical milestone2 component1
#90 Beta release: user documentation due 11-15 [1hr] Helen Colin task critical milestone3 component1
#93 Beta release: presentation 11-17 [2.5hr] everyone task critical milestone3 component1
#108 Management plan update due 11/1 [1 hr] Helen task critical milestone3 component1
#116 government income from tariffs not calculated correctly pmccormack defect critical component1
#119 level popup images inconsistent with model goals pmccormack defect critical component1
#120 game doesn't end again since somebody didn't update before committing pmccormack defect critical component1
#124 the save and load buttons don't work yet slevine defect critical component1
#125 the end-turn popups are inconvenient for testing hwu defect critical component1
#126 the buttons don't appear in the correct location in the event popups pmccormack defect critical component1
#136 the high score button doesn't work slevine defect critical milestone3 component1
#149 cannot load high score list - pickel misspelled pmccormack defect critical milestone4 component1
#154 you always get a high score pmccormack defect critical milestone4 component1
#155 high score dialog uses a lot of cpu pmccormack defect critical milestone4 component1
#171 no objective in infobox after winning - makes game crash pmccormack defect critical milestone4 component1
#173 objective popup text sometimes covered by button, done button not in right place pmccormack defect critical milestone4 component1
#174 tariff hint text under objective button somebody defect critical milestone4 component1
#182 after tax popup should appear after new game started pmccormack defect critical milestone4 component1
#1 Customer Elicitation Report somebody task major milestone1 component1
#2 Setup initial trac with team member info/other info somebody task major milestone1 component1
#3 Create reasonable project goals/longterm plan somebody task major milestone1 component1
#4 High Concept report somebody task major milestone1 component1
#5 Customer Elicitation on 9/6 somebody task major milestone1 component1
#6 Write elicitation report somebody task major milestone1 component1
#9 Write up detailed requirement specifications Helen task major milestone1 component1
#11 Decide on high priortiy policies somebody task major milestone1 component1
#13 Game Use Cases somebody task major milestone1 component1
#14 Technology Assessment somebody task major milestone1 component1
#16 Prototype Paul, Stephen task major milestone1 component1
#17 Proposal Helen, Colin task major milestone1 component1
#18 Game Treatment Colin task major milestone1 component1
#19 Management plan update 9/6 somebody task major milestone1 component1
#20 Update Teacher on TWiki Blog (week of 9/13) somebody task major milestone1 component1
#21 develop Map, Resource, Trade Route classes Paul task major milestone1 component1
#26 Management Plan 9/22 Phase 2 Risk Analysis hwu task major milestone2 component1
#28 Initialize Game - Alpha Release somebody task major milestone2 component1
#29 Initial Trade Setup - Alpha Release somebody task major milestone2 component1
#30 Display Map and Interface - Alpha Release somebody task major milestone2 component1
#31 Play Game - Alpha Release somebody task major milestone2 component1
#32 Make Tax Policy - Alpha Release somebody task major milestone2 component1
#33 Display and Update Meters - Alpha Release somebody task major milestone2 component1
#34 Hover actions - Alpha Release somebody task major milestone2 component1
#35 End Game - Alpha Release somebody task major milestone2 component1
#36 Write basic AI - Alpha Release somebody task major milestone2 component1
#40 1st Architectural Design Draft: Design Analysis Due 9-27 [1 hr] somebody task major milestone2 component1
#41 Prototype. UC Play Game: create turn mechanism, button. [goal = 9-27, t = 1-2hrs] Paul, Colin task major milestone2 component1
#42 Prototype. UC Make Policy: create popup window describing policy details [goal=9-27 t =1-2hr] hwu task major milestone2 component1
#46 Prototype writeup due 9-27 [t=30min] Colin task major milestone2 component1
#57 Prototype. UC Meters: choose concrete level goals for each meter [goal = 10-4, t = 1 hr] pmccormack task major milestone2 component1
#58 Prototype. UC Meters: implement functions to set UI meter levels [goal = 10-4, t = 2-3 hr] Colin task major milestone2 component1
#59 Prototype. UC Meters: update meters from country stats during turn [goal = 10-4, t=30min] Colin task major milestone2 component1
#60 Prototype. UC Make Policy: write instructions in info box for implementing policy [goal = 10-4, t = 1hr] Paul task major milestone2 component1
#68 Final UI Design Due 10-11 [30min] hwu enhancement major milestone2 component1
#70 Test Plan: Economic Model Due 10-11 [1hr] pmccormack task major milestone2 component1
#73 Prototype. UC Play Game: Tutorial [goal=10-11, t=4hr] Helen, Colin task major milestone2 component1
#74 Prototype. UC Play Game: Hover [goal=10-11, t=1hr] hwu enhancement major milestone2 component1
#79 Test plan implementation Stage I Due 10-20 [1 hour] somebody task major milestone2 component1
#83 Alpha release Executable: Refactor Due 10-25 [4 hr] Everyone enhancement major milestone2 component1
#84 Alpha release Executable: Text Content Due 10-25 [1hr] pmccormack task major milestone2 component1
#85 Prototype: provide more information about buttons hovered over [1-2 hrs] Colin enhancement major milestone3 component1
#86 Execute test plan: First iteration due 11-1 [1.5 hr] Paul task major milestone3 component1
#87 Prototype: choose meter goals for each level [1.5 hr] somebody task major milestone3 component1
#88 Prototype: add win event [.7 hr] somebody enhancement major milestone3 component1
#89 Beta release: executable due 11-15 [1hr] stephen task major milestone3 component1
#91 Beta release: user survey 11-15 [2hr] Everyone task major milestone3 component1
#92 Beta release: user survey analysis due 11-22 [1.5hr] hwu task major milestone3 component1
#95 Beta release: add game ending due 11-1 [2 hr] somebody task major milestone3 component1
#96 V1 Release: Framework for AI due 11-8 [2 hr] somebody task major milestone3 component1
#97 Beta release: storyline popups due 11-15 [2 hr] hwu task major milestone3 component1
#98 Beta release: only pass window around (refactoring) due 11-15 [3 hr] Stephen defect major milestone3 component1
#99 Alpha release: Documentation Due 10-27 [3 hours] Colin task major milestone3 component1
#100 Alpha release: Presentation Due 10-27 [2 hours] everyone task major milestone2 component1
#101 Beta Release: decide on level goals [1-1.5 hr] everyone defect major milestone2 component1
#102 add level objective text to infobox [.5 hr] Paul defect major milestone2 component1
#103 Testing Review Package: Intro, Agenda, Criteria due 11-3 [1 hr] somebody task major milestone2 component1
#104 Testing Review Package: Risk Analysis due 11-3 [1 hr] somebody task major milestone2 component1
#105 Testing Review Package: Rational, Tests, Test Results due 11-3 [1 hr] somebody task major milestone2 component1
#106 Testing Review due 11-3 [1 hr each member] everyone task major milestone2 component2
#107 Testing due 11-8 [1 hr] somebody enhancement major milestone2 component1
#109 High Score Feature due 11-22(cont) [3 hrs] slevine task major milestone3 component1
#112 Prototype Assessment due 11-8 [30min] Colin task major milestone3 component1
#113 Blog Update due 11-8 [30 min] Helen task major milestone3 component1
#115 highlighted icons become unhighlighted when pressed but not released on (not actually clicked on) pmccormack defect major component1
#118 game doesn't end yet pmccormack defect major component1
#122 the last level is too short for enough events to appear pmccormack defect major component1
#123 the event popups don't do anything yet pmccormack defect major component1
#127 the font in the infobox is unreadable pmccormack defect major component1
#128 Beta: implement event popup effects [2 hr] pmccormack task major milestone3 component1
#130 Beta: add options button to main menu [3 hr] hwu, pmccormack task major milestone3 component1
#131 Test Plan Response Due 11-5 [1 hr] everyone enhancement major milestone3 component1
#132 The "DONE" and other buttons for embargoes appear in the turn summary popup during the last objective somebody defect major milestone3 component1
#133 high score button doesn't have hover image pmccormack defect major milestone3 component1
#135 There is no way to restart the game once you lose pmccormack defect major milestone3 component1
#137 Management plan update due 11/15 [1 hr] hwu task major milestone3 component1
#140 Testing due 11-22 [1 hr] pmccormack task major milestone3 component1
#145 v1: add line on meters to show projected meter levels somebody defect major milestone4 component1
#150 subsidies not deducted during protest pmccormack defect major milestone4 component1
#151 arrow doesn't appear on meters if target is above maximum value pmccormack defect major milestone4 component1
#152 should there be a limit on number of high scores? slevine defect major milestone4 component1
#157 Testing due 11-22 [1 hr] everyone defect major milestone3 component1
#160 Management plan update due 11/22[[1 hr] Helen defect major milestone3 component1
#161 Management plan update due 11/22 [1 hr] Helen defect major milestone3 component1
#162 Management plan update due 11/29[1 hr] pmccormack task major milestone4 component1
#163 Code Review Package due 12-1 [t = 1 hr] Stephen enhancement major milestone3 component1
#164 high score text currently goes past end of box [fixed in current version] slevine defect major milestone4 component1
#165 Prototype Update: Hover tutorial [t = 1 hr, goal = 12-6] pmccormack task major milestone3 component1
#166 V1: make popup for objective button [1 hr] pmccormack defect major milestone4 component1
#168 Code Review due 12-6 [t = 1 hr each] everyone task major milestone4 component1
#170 Testing due 12-6 [1 hr] everyone task major milestone4 component1
#172 objective not shown immediately after tutorial pmccormack defect major milestone4 component1
#176 Code Review Package: Intro and Agenda Due 12-1 [t = 1hr] Colin task major milestone3 component1
#177 Code Review Pkg Criteria and Rubric due 12-1 [1.5 hr] Helen enhancement major milestone3 component1
#178 Code Review Pkg Class Diagram/Code Policy due 12-1 [1hr] Stephen task major milestone3 component1
#179 Code Review Pkg writing quality control due 12-1 [30min] Paul enhancement major milestone3 component1
#180 treasury is low message on embargo popup not always accurate pmccormack defect major milestone4 component1
#184 V1: Make Release Executable slevine defect major milestone4 component1
#7 Create a game map and other graphic animations Paul, Stephen task minor milestone1 component1
#8 Test pygame development platform by implementing main screen and some buttons Paul, Stephen task minor milestone1 component1
#10 Decide on resources to include in game, economic interactions between those markets someone task minor milestone1 component1
#12 Design a game interface for initializing a policy on a trade good Stephen, Paul task minor milestone1 component1
#44 Prototype. UC Make Tax Policy [goal=9-27 t=1hr] somebody task minor milestone2 component1
#45 Group Blog Due 9-27 [t = 30min] hwu task minor milestone2 component1
#51 Second Architectural Design: Revision - Due 10-4 [1 hr] somebody enhancement minor milestone2 component1
#52 Second Architectural Design: Critique - Due 10-4 [1 hr] everyone task minor component1
#54 User test Due 10-4 [30 min] Everyone task minor milestone2 component1
#55 Blog Entry - Due 10-4 [30min] Helen task minor component1
#56 Prototype Assessment Due 10-4 [30 min] Colin task minor milestone2 component1
#61 Art for Different Popups, tariff, embargo, subsidy (also for UI Design) [goal = 10-4 t = 30 min] hwu enhancement minor milestone2 component1
#71 Blog Update 10-11 [30min] hwu task minor milestone2 component1
#72 Prototype Assessment Due 10-11 [30min] Colin task minor milestone2 component1
#75 Prototype. Text Content [goal = 11-15, t = 3hr] pmccormack enhancement minor milestone2 component1
#76 Prototype. Model Enhancement [goal = 10-4, t = 1hr] Paul enhancement minor milestone2 component1
#80 Test plan implementation stage II Due 10-25 [30min] somebody task minor milestone2 component1
#81 Blog Update Due 10-25 [30min] hwu task minor milestone2 component1
#82 Prototype Assessment Due 10-25 [30min] Colin task minor milestone2 component1
#111 Protoype: Economic Model Improvements for Gameplay goal 11-15 [2hr] somebody enhancement minor milestone3 component1
#114 background flashes when popups appear during intro hwu defect minor component1
#121 objective 3 is too hard to complete pmccormack defect minor component1
#129 Beta: add a help button [2 hr] cbundschu task minor milestone3 component1
#134 First and Thrid level take too many turns to complete pmccormack defect minor milestone3 component1
#138 Blog Update due 11/22 [30min] hwu task minor milestone3 component1
#139 Prototype Assessment due 11-22 [30min] Colin enhancement minor milestone3 component1
#141 Prototype: Change help button to say help [goal = 11-22, t = 30 min] paul enhancement minor milestone3 component1
#142 Prototype: make objectives and hints always show on screen [ goal = 11-22] hwu enhancement minor milestone3 component1
#143 Prototype: Economic model enhancements [goal = 11-22, t = 30 min] Paul defect minor milestone3 component1
#146 v1: there should be a button that shows objective when hovered over somebody defect minor milestone4 component1
#148 v1: add tutorial that highlights button functions [1.5 hr] pmccormack enhancement minor milestone4 component1
#153 missing a lot of constants in high score mechanism slevine defect minor milestone4 component1
#156 Consumer/Producer happiness can go above 100% [fixed in current version] somebody defect minor milestone4 component1
#158 Blog Update due 11-29 [30 min] Helen enhancement minor milestone3 component1
#159 Prototype Assessment due 11-29 [30min] Colin enhancement minor milestone3 component1
#167 V1: tutorial for hovering over anything and clicking on meters [2 hr] pmccormack enhancement minor milestone4 component1
#110 Prototype: End Turn Summary due 11-8 (on hold) [1 hr] Helen enhancement trivial milestone3 component1
#144 V1: add specific descriptions of policies linked to help menu [2 hr] hwu enhancement trivial milestone4 component1
#147 missing some constants in the meter drawing pmccormack defect trivial milestone4 component1
#169 V1: move help button? pmccormack enhancement trivial milestone4 component1
#175 make sure students know that policies from previous levels can still be used cbundschu defect trivial milestone4 component1
#181 high score popup could allow for more text (make it longer?) pmccormack enhancement trivial milestone4 component1

Status: assigned (1 match)

Ticket Summary Owner Type Priority Milestone Component
#117 game cannot load background image in linux due to race conditions. causes crash slevine defect trivial component1

Current Goals (this week's in bold)

Goal Due Date Status
Customer Elicitation Report 9/13 Completed
Game Use Cases 9/13 Completed
Technology Assessment 9/13 Completed
Management II 9/13 In Progress
Weekly Meeting Progress Report ?
Blog Update ?
Prototype ?
Proposal ?
Treatment ?

Completed goals

  • Update track with team member info / other info
  • Create reasonable project goals / longterm plan
  • Do competitive analysis and high concept reports
  • Install python and pygame on all computers
  • Perform customer elicitation on 9/6
  • Write elicitation report
  • Create game map and other graphic animations
  • Test pygame development platform by implementing main screen and some buttons
  • Write up detailed requirement specifications
  • Decide on resources to include in game, economic interactions between those markets
  • Choose high priority policies from elicitation report and discuss economic consequences of each
  • Design a game interface for initializing a policy on a trade good

Week Three

Current Goals

  • Deliverables
    • develop an initial game prototype
    • create a game proposal, including summarized information from previous deliverables
    • describe the game in a Game Treatment for the middle school students
  • Other Goals
    • Decide on which language to use
    • discuss in detail underlying economics in game
    • decide how to implement shared resources
    • Create more graphic animations
    • Test pygame development platform by implementing main screen and some buttons
    • Decide on resources to include in game, economic interactions between those markets

Week Two

Completed goals

  • Do competitive analysis and high concept reports
  • Choose high priority policies from elicitation report and discuss economic consequences of each
  • Write elicitation report
  • Create game map and other graphic animations
  • Write up detailed requirement specifications

Incomplete Goals

  • Test pygame development platform by implementing main screen and some buttons
  • Decide on resources to include in game, economic interactions between those markets
  • Design a game interface for initializing a policy on a trade good

Week One

Completed goals

  • Update track with team member info / other info
  • Create reasonable project goals / longterm plan
  • Install python and pygame on all computers
  • Perform customer elicitation on 9/6