Schedule
4/1/01 Annie and Neilsen – put up the basic
website with image maps
Elmer and Hang – have a database ready for
integration with the website
4/4/01 Integrate the database with the website
and incorporate the room claiming functionality with security
4/8/01 Finish testing the database and the
website
4/13/01 Incorporate priority and pulling
functionalities
4/17/01 Finish testing the priority
functionality
4/24/01 Incorporate all other features such as
locking, administrative capabilities, email, and help pages
4/28/01 Be completely done, including testing of
the above additional features